Free PMP practice test

12 original questions written by our editors against the official PMI exam domains. They are not real exam questions. Pick an answer to see the explanation.

0 / 0 correct

  1. People

    Two senior developers on your hybrid team keep arguing in stand-ups about code review standards, and the disagreement is slowing work on the current iteration. What should you do first?

    Show answer

    Answer: B. Managing conflict starts with understanding its source and facilitating an agreed resolution that the team owns, such as a working agreement. Escalating or reassigning people skips the team's ability to resolve it. Imposing a standard may end the argument but does not build buy-in.

  2. People

    Halfway through a project, a new sponsor takes over. In her first meeting she describes the project's purpose quite differently from the approved charter. What is the best action?

    Show answer

    Answer: C. A mismatch in understanding the vision should be surfaced and resolved with the people who own it before anything else changes. Ignoring it risks delivering something the sponsor will not accept. A change request is premature until the vision is agreed, and a status report does not address the misunderstanding.

  3. People

    A regulatory affairs manager has high influence over your product's approval but rarely attends design reviews. Last week he raised objections late, causing rework. What should you do?

    Show answer

    Answer: A. High-influence stakeholders need engagement tailored to their needs and availability, and the engagement plan should reflect that. Removing him guarantees more late surprises. Forcing attendance or adding detail to a report does not address why he is not engaging.

  4. People

    The only team member who understands a legacy system integration has resigned and leaves in six weeks. Integration work continues for another four months. What is the best response?

    Show answer

    Answer: B. Knowledge transfer works best when it starts early, focuses on critical knowledge and combines hands-on pairing with documentation others can access. A last-week document captures too little. Delaying departure is outside your control, and accepting the risk ignores an obvious threat you can reduce.

  5. Process

    Your project includes a medical device whose hardware requirements are fixed by regulation, and a companion mobile app whose features will change based on user feedback. Which development approach fits best?

    Show answer

    Answer: C. Stable, regulated requirements suit predictive planning, while evolving requirements suit iterative delivery, so a hybrid approach matches each part to its needs. Fully predictive planning would force constant change requests for the app. A fully agile approach ignores the fixed regulatory constraints, and waiting delays value.

  6. Process

    At a status review, your project shows a cost performance index (CPI) of 0.85 and a schedule performance index (SPI) of 1.05. How should you describe its performance?

    Show answer

    Answer: C. A CPI below 1.0 means each unit of money spent is earning less than planned value, so the project is over budget. An SPI above 1.0 means more work has been completed than planned at this point, so it is ahead of schedule. The other options reverse one or both indices.

  7. Process

    Your team has a fixed release date and more backlog items than it can finish. Stakeholders disagree on what matters most. How should you decide what the team works on?

    Show answer

    Answer: D. Value-based delivery means prioritizing with stakeholders by business value and delivering the most valuable work first, so the fixed date still yields the most benefit. Arrival order and ease ignore value. Spreading effort evenly risks finishing nothing completely by the release date.

  8. Process

    You need an outside specialist to start next week on a short, two-month engagement while requirements are still being explored. Your organization wants to limit its financial exposure. Which contract type fits best?

    Show answer

    Answer: A. Time and materials suits short engagements where the scope is not yet defined, and a not-to-exceed limit caps the buyer's exposure. Firm fixed price needs well-defined scope, which you do not have. Cost plus percentage of cost gives the seller no reason to control costs, and a multi-year award-fee contract is far too heavy for two months of work.

  9. Process

    The customer has accepted the final deliverables of your project. What should you do next?

    Show answer

    Answer: B. Closure includes formal approval, confirming readiness for transition, final lessons learned, and closing procurements, finances and resources. Releasing the team or archiving documents first leaves these activities unfinished. A follow-up project is a separate initiative and does not close this one.

  10. Business Environment

    On the predictive part of your project, a customer vice president asks a developer directly to add a new reporting feature. The developer tells you about it. What should you do?

    Show answer

    Answer: A. Requested changes to baselined work go through change control, with an impact analysis so the right people can approve or reject them. Adding it informally creates scope creep. Refusing outright ignores a possibly valuable request, and updating the baseline before approval bypasses governance.

  11. Business Environment

    Your risk register lists late delivery by a key supplier as a risk, with a planned response of using a pre-qualified backup supplier. The supplier has now confirmed a three-week delay. What should you do?

    Show answer

    Answer: A. The risk has occurred and is now an issue, so you apply the response you already planned, track it as an issue and communicate. A new workshop or waiting wastes the time the plan was meant to save. Re-baselining accepts the full delay without trying the planned response.

  12. Business Environment

    A new data privacy regulation has been announced that takes effect before your system goes live. It may affect where customer data can be stored. What is the best action?

    Show answer

    Answer: C. Changes in the external environment should be assessed for their impact on scope and backlog, with compliance needs prioritized and stakeholders informed. Waiting leaves less time to respond. Cancelling is an overreaction before any analysis, and rushing to go live early does not remove the compliance obligation.

Next step: read the PMP exam guide for the format, domains and how to prepare, and check the exam cost.